According to the press statement released from
Minister of Works, Mike Onolememem he said: "The Federal Government today,
terminated the concession of the Lagos-Ibadan expressway granted to Bi-Courtney
Consortium on 8th May, 2009. The termination of the concession agreement by
Bi-Courtney consortium and especially the failure of the company to reach
financial close as provided for in the agreement.
Due to the senseless carnages on this important
expressway which is part of Arterial Route A1, the Federal Government has also
decided to embark on the emergency reconstruction of the expressway.
Consequently, the Federal ministry of Works has
engaged the services of Julius Berger Plc and R.C.C Nigeria Limited to commence
work immediately on the reconstruction of the expressway.
While Julius Berger would handle section 1: from
Lagos to Shagamu interchange, RCC Nigeria Limited will be responsible for
section II: from Shagamu to Ibadan.
The Federal Government wishes to assure that while
it will continue to uphold the sanctity of contracts entered into by the
Federal Government, it will not shy away from implementing provisions of the
contract agreement dealing with non-performance on the part of the contracting
party. Continue after the cut:
The legal implications of this termination have been
carefully considered by both the Federal Ministry of Works and indeed the
Federal Government. If you recall, we have been on this issue for quiet
sometime now and we have meticulously followed the concession agreement, the
provision of relevant clauses of the agreement.
We have complied fully with the provisions of this
agreement. We have had cause even in the past to write the concessionaire to
detail the breaches which it had committed in this agreement in this particular
transaction and we have also followed the minimum and maximum number of days
the contractor was expected to remedy the situation but failing which the
Federal Government had no alternative but to take this course of action.
For your information, under this concession, the
construction period is supposed to last for four years and the four years will
come to a close in about six months’ time and right now there is nothing on
ground to suggest that the company is capable.